Saturday, April 02, 2011

The Foundation is Complete

This morning Ron and his crew removed the forms from the foundation walls. We are now ready to start building. The materials are scheduled to arrive Wednesday or Thursday. We are still trying to get someone to cut an access hole from the existing basement into the crawl space.











Wednesday, March 30, 2011

Holey Holey Holey


Jim, the excavator showed up at 7:30 this morning and began digging. 5 dump truck loads of dirt were hauled away to make room for the foundation and crawl space beneath the addition.





Tuesday, March 29, 2011

My Apologies for Not Posting


Friday through Monday were spent demolishing the upstairs guest bathroom. Here are a few pictures, before and after.





Here are a couple of after pictures of the bathroom:





On Monday, the excavator called saying he would be here on Wednesday... this IS commitment. We had to take down part of the chimney chase so that they can get underneath it with the foundation forms. Thank God Josh was available to help. One minor glitch... when they ran the pipe for the gas fireplace, they ran it right out under the chase. We will have to relocate the gas line into the existing structure.




I cannot believe what lies ahead!

Thursday, March 24, 2011

Finally -- Let the fun begin!


Today, three weeks after submitting the plans for the addition, I received the building permit. Tomorrow the summer project begins. Tonight we head to Epic for dinner.


Sunday, March 13, 2011

Where there once was a door, there is now a stud wall. The closet has shifted 3 feet to the left.


Saturday, March 12, 2011

Today's Progress


After planting a couple of trays of seeds including additional tomatoes, peppers, State Fair Zinnias, and African Daisies. I gathered up by tools of destruction, and set out on a wrecking
rampage.

I have now come to the tub surround and plumbing. I will not be touching these until I have my permit.




Friday, March 11, 2011

Update


Last Thursday, March 3rd, the architect delivered the final plans, along with the engineers documents. Quite a body of work for a simple addition. I immediately took two sets of plans down to Sandy City for them to review so I may get my building permit. I am still waiting to hear from the city.

On Friday the 4th Alina and Nick arrived for their annual skiing outing. They had to hurry back a day early to take care of some business, and they left at 10:30 this morning. I got right to work.

Here are the before and after shots of todays destruction.


Sunday, February 13, 2011

Very close now
... a final few cosmetic things and the plans will go to the engineer.





Friday, February 11, 2011

For those who have difficulty understanding the proposed second story space, here are some additional pictures.

Wednesday, February 09, 2011

We got the final plans from the architect today.  Major changes are in the upstairs where we are pretty much into a second story again.  Two remaining questions... do we make the guest shower into a steam room as well, and do we put a window in the guest shower?

Thursday, February 03, 2011

The Empty space...

...demands an addition!


Real Commitment


The addition project really got underway to day when we pulled the trigger on the Cottonwood tree.  The tree would probably have had to come down within a few years anyways, and we would certainly kill it when we dig the foundation for the addition as the side yard is filled with its roots.



8:00 am


8:30 am


9:00 am


9:30 am


10:00 am


10:30 am


11:00 am



Lunchtime