Monday, May 23, 2011

So here is what's happening


Of the last ten days there have been two which were rain free. Sometimes we have showers, sometimes torrential downpours, sometimes it just rains all day. I spend fully half of my time (if not more) dealing with water issues. I would like to keep the project somewhat dry, but am largely unsuccessful.


These pictures were taken yesterday in the afternoon, I am fairly sure we had some rain in the morning. We have started putting the roof sheathing on the lower level, and need to get thqt completed before we attempted to put up the trusses for the second story roof. Until we get the second story roof up and the sheathing on it, we are going to continue to have serious problems keeping the project dry if it continues to rain as it has been. I have tried several different approaches to try to keep th second floor dry and the water diverted away from the structure (otherwise it leaks though onto the main floor kitchen and bathroom area, and thence down into the crawl space. In general all attempts have been less than successful. I have tried a new approach today and am hopeful of a better result. Of course now that I have gotten new plastic on, the wind is starting to blow... I do not think the plastic can survive even a mild wind.




We placed the post which will support the roof beam on the front porch. I used a four foot "Sono" tube, but it was not quite high enough, so we improvised with a Heineken Carton and some duct tape.



And here are a few more pictures of the project... some taken from my roof.








Sunday, May 15, 2011

May 15TH Progress Report


Almost two weeks have passed. Lots of time has been spent trying to keep water off the project and out of our house. I have not been very successful. None-the-less, Josh and I are making progress.







Monday, May 02, 2011

May Day Progress Report


The entire day was spent working on the chimney chase. We cannot finish the subfloor on the second story until the chase is removed.




I also ruined one of the second floor joists by cutting it an eighth of an inch too short, and I want to add an additional joist under the bathtub. So I had to order two more 18 foot joists which should be available on Tuesday.

Today we will have to work on getting the chase down today and building the other main floor walls. I am pretty sure we can determine the height of those walls, since we now know the exact height of the top of an existing roof joist above a spot on the deck, So we just need to measure the distance from that spot to the wall in question, and deduct 5" for every 12" of distance.

Saturday, April 30, 2011

Progress Report

April 30, 2011


It has been almost two weeks since I last reported on progress. Because of the terrible weather (cold and rainy), and Josh having to work quite a bit during the last two weeks, it seems that little progress is made. Following is a synopsis of what has happened over the last two weeks.

When we last left off, most of the work on the subfloor was complete. I was able to complete the subfloor by the 19th in preparation for Josh's return on the 20th for a couple of days.


With Josh back, we were able to start putting up the walls on the main floor. By the end of day on the 20th we had gotten the south exterior wall up, and several of the interior walls to help support it.


The 21st saw more progress. But by the end of the day we were besieged by cold rainy weather again. Very discouraging, but at least it is not tornadoes. You can see the water standing on the sub-floor.



This is a detail photo of the water damage that has occurred to the chimney chase over the lost 24 years. While it looks like it has been burned... it is really just rotten. Slow oxydation as opposed to rapid oxydation.




While josh was gone I was able to get a lot of stucco removed. I also worked on rerouting the broadband cable into the addition crawlspace, and spent a whole day in a cramped uncomfortable position putting lighting into the crawl space. I also converted the light by the garage door (adjacent to the addition) into a electrical outlet.

When Josh returned, the materials had not yet arrived so we spent the morning of the 27th getting rid of the above mentioned garage door, and preparing the posts that would support the beam. The folks at Home Depot have been really great to work with on this project. They made a special trip on the 27th to deliver the materials we would need to keep going, including the beam. After delivering the materials they actually helped us raise the beam into place. You can see it in these pictures.



The 27th was a nice day.


The 28th was a good day as well. I was able to work in tee shirt and shorts. I was able to begin putting up the floor joists on the second floor after I had attended to several other tasks that needed to be accomplished.



Among those other tasks was nailing the seismic straps on the south wall. There are three of them and they each take 30 16d nails. This is a job that has to be done by hand. It took me a while.



The weather of the 29 was cold and we had snow flurries all day long. None the less I continued to work on the second story joists and rim board. I shorted my self on the number of joists required, and ruined one through a mis-cut, so I will have to wait until Tuesday before the last of the floor joists goes up and we can install the second floor sub-floor.

This morning this is what I saw.




Sunday, April 17, 2011

Subfloor Nears Completion

Was able to get a couple of things done today before putting down more subfloor. Tired tonight.

Saturday, April 16, 2011

Main subfloor going down


Yesterday, we completed the joists and rimboard and started on the subflooring. This was a tough ten hour day. Josh had been hoping we could finish the subfloor before he had to go back to work, but this is where we ended up on Friday night.


Josh had to go back to work today. This morning I worked on the last remaining pieces before the new washer and dryer could be installed in the roughed out laundry room upstairs. I did the final soldering of the washing machine hook-up, and did the wiring required to send the power to the dryer upstairs.

Then I went outside (around noon) and was able to put down some additional subfloor. I work at about half the speed of Josh, but did mange to get another row of the sub-floor set. Josh comes back on Tuesday afternoon. Perhaps I will have the subfloor done, and the stucco removed on the next level. We will see.

Thursday, April 14, 2011

Progress


Josh is home for a couple of days. I do what I can when he is working, but real progress is not made until he is here to lend his back and his knowledge. While he was working, I was able to build the pony walls, to get all of the cabling rerouted, and clean up some of the mess of rotten wood... or at least try to find where all of the rot is, so that we can repair it. Today we repaired the wood around the window in the garage, and, in fact, got rid of the garage window. We also placed most of the joists for the main floor. Our significant accomplishment was that we were able to place the beam that will support the load bearing wall between the main floor bedroom and bathroom. It must have weighed over 500 pounds. The weather has been absolute crap. It was snowing thins morning, and while it cleared this afternoon, it was very raw.



Saturday, April 09, 2011

On Hold Again


Some progress was made during the week, but not as much as we had hoped. By this time we had thought we might have the main floor joists on and the sub-floor added. Not to be.

On Wednesday, the excavator came and backfilled the foundation.


He also left a truck full of gravel which needs to be spread out on top of moisture barrier (plastic) to give a better ground covering in the crawl space. Gage has begun the process of spreading the gravel. Of course if I put the plastic down in the whole crawl space and it rains, then we will have a pond in the crawl space. It seems that vapor barrier works both ways.


On Thursday, the concrete cutters came to cut the access to the crawl space into our basement. We wanted the access inside rather than outside. It will be hidden (eventually) behind a regular looking door. We had to tear into the basement anyways at some point to get to the waste stack. The round hole is where the waste pipe will go through the foundation into the existing basement.




The materials for the main floor were also delivered on Thursday and Josh and I were able to get some of the sill plates mounted before the thunder and snow started.

Now the materials sit in my and Joshs' driveways under a cover of snow.




I have done some work inside to try and bring some order of normalcy back to the house... but not much. I will be working on getting the unfinished laundry room ready for the new washer and dryer, so we can get rid of the existing laundry room and make the changes to the mainfloor of the house that will be required.

Sunday, April 03, 2011

Project on Temporary Hold


70 degrees yesterday. A foot of snow today. I guess it is back to the inside work for a couple of days.

Saturday, April 02, 2011

The Foundation is Complete

This morning Ron and his crew removed the forms from the foundation walls. We are now ready to start building. The materials are scheduled to arrive Wednesday or Thursday. We are still trying to get someone to cut an access hole from the existing basement into the crawl space.